Case Study 5: Sour Water Pipeline Repairs
Incorrect.
The energy control procedure provisions require the documentation of procedures that
clearly and specifically outline elements described in 29 CFR
1910.147(c)(4)(ii). Because of the need to follow specific steps to successfully
lockout a machine or piece of equipment as illustrated by this incident, a documented
procedure is necessary for most energy control situations.